Installed Capacity
0 MW
Status
In Operation
Ownership
Transferred
Substation Rabäcken connects MB1101 – Phase 1 und Phase 3 wind farms to Svenska Kraftnät’s 400kV transmission grid. The installed grid connection capacity of 1.700 MW makes Rabäcken one of the most powerfull substations in Scandinavia. The respective grid company Markbygden Net AB was established by Svevind AB in 2010 and acquired by Ellevio in 2023.